Our Norwegian project keeps getting extended — when does that become a tax problem?
At 12 months for building and installation projects — the extension nobody re-analyzed is the classic way foreign contractors acquire a permanent establishment and retroactive Norwegian corporate tax. Each extension is signed for good commercial reasons by people who have never heard of the rule. The fix costs 30 minutes per extension: re-run the PE analysis before signing, not in month 14.